7:33am- dozer work to be done today along with more testing. 

Crew at MH E26. 

7:59am- line now on test from MH E26 to E25. Approximately 95 min test. 

9:33am- line passes air test from E26-E25. 

11:40am- line now on test from MH E26 to E27. Approximately 92 min test. 

1:11pm- line passes air test from E26 to E 27. 

3:11pm- line here at MH E28 now on test back to E27. Approximately 37 min test. 



3:48pm- line passes air test from MH E28 to E27. 

4:29pm- test ball will be moved to other pipe here at MH E28 so that testing of the line to E29 can begin first thing in the morning. 