7:33am- dozer work to be done today along with more testing.
Crew at MH E26.
7:59am- line now on test from MH E26 to E25. Approximately 95 min test.
9:33am- line passes air test from E26-E25.
11:40am- line now on test from MH E26 to E27. Approximately 92 min test.
1:11pm- line passes air test from E26 to E 27.
3:11pm- line here at MH E28 now on test back to E27. Approximately 37 min test.
3:48pm- line passes air test from MH E28 to E27.
4:29pm- test ball will be moved to other pipe here at MH E28 so that testing of the line to E29 can begin first thing in the morning.