7:09am- crew will begin laying more pupe today and set MH E32. 8:05am- breaking rock first thing! 9:07am- 1st joint going in. 10:26am- more rock breaking occurring again. 11:31am- 2nd joint now in as rock breaking will continue. No blasting occurred in this location. Breaking 6’ to 7’ of rock out. 12:51pm- preparing to remove broken rock from MH E32 location now. 1:40pm- excavator digging to try and find shot ditch leaving MH E32 area. 2:59pm- crew is preparing to call it a day. MH E32 will wait to be set on Monday hopefully. A lot of rock had to be broke out today.
7:20am- equipment will be moving back up to MH E44 area to begin line work again today. 8:68am- crew still moving materials closer to MH E44 area. 9:45am- tops and covers going on manholes previously set as they climb towards MH E44. 10:50am- now back to digging upstream of MH E44. 11:19am- 1st joint of pipe for today so far! 11:56am- 2nd joint getting gravel. 1:15pm- #3. 2:23pm- more gravel is getting moved closer to area of work. 2:41pm- 5th joint so far getting gravel. 3:31pm- digging for #7 now. 3:50pm- gravel going on #7. 5:00pm- went to lower field on Rittenhouse to look at dirt leveled out last week near MH A6. Owner not happy. Wants more work to be done says it dry enough… After driving through it. Sent picture to FlatCreek so that they can schedule it this week hopefully.
Comments
Post a Comment