Turkey Creek Ph 2 - Interceptor


7:05am- crew is getting around to begin digging to set MH E55 this morning. 

8:27am- grading gravel for MH E55. 

8:56am- MH E55 base now going in place. 

9:16am- MH E55 now tied to line with a 7’ piece of pipe. 

Line is also lamped by laser back to MH E56. 

10:30am- after a long wait to get Ram-nek warm enough to use; barrel section is now getting placed on MH E55 base. 

11:37am- alignment now completed to MH E54 and digging is now underway from from MH E55. 

1:56pm- crew has now set 1st joint downstream of MH E55. 

2:49pm- 2nd joint now going in. 

3:42pm- 3rd joint now placed. 

4:41pm- roadway cleanup is done and passable for traffic tonight. 