7:02am- crew will be laying more pipe today, hopefully arriving at MH E54 by end of day.
9:07am- digging at MH E54 area now with the 2nd joint of the day now placed.
10:23am- gravel is leveled for MH E54 base with 3rd joint set.
11:12am- MH E54 base now set and tied to line with a 9’ piece of pipe.
Line is also lamped by laser back to MH E55.
12:41pm- alignment to MH E53 is done as digging is back underway.
1:20pm- pipe now in downstream of MH E54. 5 full joints now laid.
2:49pm- 8 joints now laid. Dirt has changed and is easier digging this afternoon.
4:02pm- 10 joints placed.
4:50pm- 11 joints and the crew will clean up roadway to call it a day.