Turkey Creek Ph 2 - Interceptor


7:07am- digging teeth are getting changed out first thing this morning. More pipe to ho in as crew will be approaching MH E53. 

8:39am- 1st joint placed as crew shoots grade for MH E53. 

9:20an- MH E53 base is placed and line is lamped by laser back to MH E54. 



10:41am- crew prepares to cut bell off pipe to begin laying from MH E53 downstream. 

12:21pm- 4joints now placed. 

2:16pm- 7 joints now placed as crew approaches MH E52 location. 

3:14pm- 9 joints placed today. The crew will stop laying pipe due to being at MH E52 location and they do not have the manhole here. Cleanup of roadway and area will round out the day along with barricading ditch. 

3:35pm- Barricades are up. 