Turkey Creek Ph 2 - Interceptor


7:07am- crew is back at MH E51 to get manhole set and begin laying pipe today. 

7:34am- crew is leaving this manhole(E50) here at E51 location due to the original E51 manhole not getting back here until later today.  There is a difference of 4” and 2* in maholes. 

Line is lamped by laser back to MH E52. 
9:25am- graveling 2nd joint now out of MH E51. 

10:44am- 5th joint laid just after tunneling under culvert. 

11:54am- 7 joints placed with newly built MH E50 arriving onsite. 

1:12pm- grading gravel for #9. 

3:46pm- 152’ of pipe is laid so far today tying manhole E50 to line. Crew will get aligned to MH E49 now. 

Line is also lamped by laser back to MH E51. 

4:39pm- breaking rock for 1st joint out of E50. 

5:14pm- barricades are up for the end to the day. 