Turkey Creek Ph 2 - Interceptor


7:16am- crew digging to lay more pipe and set more slope anchors. Anchors placed yesterday to be poured today. 

9:03am- jack hammer was used to get some rock out of the way this morning before 1st joint is placed. Crew now awaiting concrete for slope anchors. 
9:19am- concrete has arrived. 







3 poured as gravel is placed on exposed pipe now. 

10:45am- 1st joint laid today now with more rock to be broke out. 



12:57pm- 2nd joint for today, and another slope anchor is built with rebar. More rock breaking to occur. 



3:07pm- 4th joint now placed as last slope anchor is created.



3:23pm- concrete going in now. 



3:46pm- 3 anchors now completed. 

4:50pm- 5th joint for today as backfill will round out the day. 











 