Turkey Creek Ph 2 - Interceptor


7:21am- digging, pipe laying and slope anchors to continue today as MH E47 area is approaching. 

8:28am- after some rock breaking this morning, the first joint for today is getting ready to be placed. 

9:37am- still digging and breaking rock while fencing is getting some attention. 

11:02am- still on 1st joint due to the amount of rock breaking needed. 

12:39pm- 3 joints now placed. 

2:06pm- 4th joint now set and more slope anchor work begins. 



3:44pm- 5th joint placed and MH E47 is set in place. Manhole was moved 3’ downstream to help avoid power pile and not ise a 3’ piece to connect. 



Line at is lamped to MH E46. 
4:38pm- cleanup will round out rest of the day. 