Turkey Creek Ph 2 - Interceptor
7:33am- crew getting gravel graded out for joint #1 as they will be at MH E48 today.
8:32am- rock is broke out for 2nd joint of the day to be installed.
9:32am- 3rd joint placed as they are now roughly two joints away from E48 MH location.
10:25am- 4th joint set and more rock as they dig for MH E48.
11:47am- almost dug out for MH E48.
12:52pm- 5th joint hoes in so that MH E48 can be set.
1:16pm- MH E48 is set and aligned to MH E47. Line is also lamped by laser back to MH E49.
3:02pm- MH E48 is stacked out now.
3:24pm- MH E47 gets a 16” barrel section added and lid placed.
4:00pm- crew has placed barricades back up around MH E48 area and will call it a week.