Turkey Creek Ph 2 - Interceptor
Grouting will resume today at MH E26.
7:43am- culvert at MH E32 will need to be covered back up so crew can get to MH E26 area. Excavator will used to do repair once it is started.
8:16am- crew now at MH E26 to continue with grouting.
10:19am- crew still working on E26. With everything being so cold, its taking longer for grouting to set up.
11:11am- MH E26 is now grouted.
12:37pm- some gravel and grit materials will be cleaned out of next manhole.
2:11pm- MH E28 now grouted.
3:37pm- crew working on MH E29.
4:02pm- MH E29 now grouted. Crew will get things picked up and make way back to Carlton through the mud.