Turkey Creek Ph 2 - Interceptor
Crew will begin testing again from MH E36 area.
8:45am- crew has pulled test balls from E36 area and brought them to MH E27 to begin manhole vacuum testing to get caught back up with the line testing.
8:59am- MH E27 passes vacuum test.
9:29am- MH E28 passes vacuum test.
9:52am- MH E29 passes vacuum test.
10:16am- MH E30 passes vacuum test.
10:50am- MH E30 passes vacuum test.
11:47am- MH E32 ring and lid leaking. Not pulling vacuum. Crew working to fix it.
11:54am- MH E32 now passes vacuum test.
12:52pm- MH E33 passes vacuum test.
1:19pm- MH E34 passes vacuum test.
1:55pm- MH E35 passes vacuum test.
2:16pm- line test getting set up for E36-36 run.
2:30pm- issue with test box today… leaking pressures off lines.
2:35pm- line now on test from MH E36-E35. Approximately 22min test.
2:56pm- line passes air test from E36-E35.
3:30pm- MH E36 passes vacuum test.
Crew bled the line and moved test balls around to be ready for additional testing tomorrow if rains hold off.
4:18pm- equipment is staged at MH E37 and covered up for the night. Crew will make their way out to Carlton before calling it a day.