Turkey Creek Ph 2 - Interceptor
7:32am- crew is getting MH E37 ready for a vacuum test as well as more line testing to be done today.
8:02am- MH E37 passes vacuum test.
9:03am- MH E38 passes vacuum test.
9:30am- line now on test from MH E39-E38. Approximately 95 min test.
11:09am- line has failed air test from E39-E38. Crew will begin process of figuring out whats wrong.
11:46am- crew has sprayed soap and checked all fittings and have concluded that maybe its just a pressure drop due to line temperature fluctuations. Air test is back underway again for approximately 95 min.
1:09pm- a leak in the return line has been located and the crew has cut it out and done a repair. Line back under test again from E39-E38. 95 mins.
2:45pm- line now passes air test from E39-E38.
4:41pm- crew still bleeding air from air test earlier. No more test will be done today.