Turkey Creek Ph 2 - Interceptor


7:10am- slow start with all the snow still onsite, but more digging and pipe laying to come today. 

8:02am- 1st joint going in as gasket is cleaned before installing. 

9:58am- 3rd joint getting placed. 

10:33am- 4th is now in place.  
11:45am- 5th is placed with rock now showing. 

1:03pm- 6th joint placed. 

2:11pm- 7th is placed and more rock breaking occurring. 

3:25pm- still on #7. Still breaking rock. I’ll be offsite rest of the day. 