7:04am- crew will begin with more rock breaking this morning as they approach MH E49 location. 

7:40am- crew was able to set 1st joint of the day, but there is a hump of rock right at the end of pipe that will get broke out. 

8:50am- 2nd joint placed and digging out for MH E49 now. 

10:13am- grade is shot on MH E49. 1/2” low. Crew has joined it to the line with a 5’ piece of pipe. 



Line is also lamped by laser back to MH E50. 
11:53am- alignment completed to MH E48 and joint of pipe set leaving MH E49. 

1:20pm- crew prepares to set 3rd joint from MH E49. 

2:30pm- 5th joint now placed for seven total so far. 

3:26pm- 8th joint for the day. 

4:24pm- 9 joints for today total. Fence is up and placed for the end of the day. Out of gravel!