6:58am- crew is back to lay more pipe today between MH E49-48.
8:03am- 1st joint now placed this morning.
8:55am- 2nd joint placed. Rock is showing in ditch again that will need broke out along with getting under culvert.
10:28am- crew went down to MH E32 area to fetch pipe they used for drainage. They will need this pipe at the top end.
11:00am- pipe is now apart and will be hauled to the top.
12:56pm- rock is broken up now and digging will resume.
3:07pm- rock is finally gone and past culvert. 5th joint for today going in.
4:00pm- crew lays 6th joint for today and places barricades back up for tonight. Quarry closing at 4pm now so cant get rock for pipe.