Turkey Creek Ph 2 - Interceptor


6:54am- crew will continue with line testing today here at MH E39. 
7:34am- line now on test from MH E39-E40. Approximately 95 min test. Grouting will now resume. 



9:23am- line passes air test from E39-40. 

11:09am- Crew still at MH E36 grouting. 


MH E35 is done. 

12:47pm- E36 is now completed. 

1:26pm- MH E39 passes vacuum test. 

2:44pm- line now on test from MH E40-E41. Approximately 93 min test. 

4:20pm- line passes air test from E40-E41. 

Crew will bleed line off and call it a day. 