Turkey Creek Ph 2 - Interceptor
6:54am- crew will continue with line testing today here at MH E39.
7:34am- line now on test from MH E39-E40. Approximately 95 min test. Grouting will now resume.
9:23am- line passes air test from E39-40.
11:09am- Crew still at MH E36 grouting.
MH E35 is done.
12:47pm- E36 is now completed.
1:26pm- MH E39 passes vacuum test.
2:44pm- line now on test from MH E40-E41. Approximately 93 min test.
4:20pm- line passes air test from E40-E41.
Crew will bleed line off and call it a day.