Turkey Creek Ph 2 - Interceptor


7:07am- crew will be working on grouting today. 

8:19am- cleaning out flowline before grouting takes place here at MH E39. 

9:30am- MH E39 now grouted. 

10:45am- pipes grouted at MH E40 as flowline work begins now. 

11:42am- MH E40 now completed with grouting. 

1:02pm- MH E41 is next for grouting. 

1:54pm- MH E41 now grouted. 

2:52pm- crew is back at MH E27 now to sand the flowline out on pipe a little due to a ripple in pipe flowline. 

4:48pm- grouting now completed in MH E27. 