Turkey Creek Ph 2 - Interceptor


Crew will be gathering things to clean out pipe today between MH E2-E1. 
8:35am- E2 manhole with standing water in it due to the silt backup. 

9:10am- pump now running at MH E1. 

9:19am- a jetter is going to be needed to properly clean pipe. FlatCreek is going to try and hire one to do it. 

11:17am- crew will enter MH E24 now to begin cleaning a section of pipe upstream. 

12:39pm- bucket and ropes being used to remove debris from line at this time. 

1:09pm- a lot of gravel has been pulled from pipe now. 
More to come. 

3:37pm- first round of gravel was raised from MH E24 and crew wanted a break from that, so now they are at MH E47 continuing with grouting. 

4:56pm- MH E47 almost grouted now. This will round out the day here. 