Turkey Creek Ph 2 - Interceptor


Waited on Ace Pipe to show at quarry to show them the way in to project. 
7:20am- Ace now onsite to begin camera and mandrel work again today. 

7:53am- going in at MH E36 to camera up to E39 and then pull mandrel back. 

8:39am- camera now at MH E39. Mandrel will be attached now and pulled back down pipe. 

9:04am- FlatCreek crew at MH E1 pumping water that was put in line yesterday to try and help loosen up silt. 

9:43am- mandrel at MH E36 now. 

9:52am- camera at MH E33 now from E36. 

10:34am- mandrel now at MH E33. 

11:46am- camera going in at MH E29 now upstream to MH E33. 

12:25pm- mandrel is getting attached at E33 to be pulled back to E29. 
12:41pm- mandrel now at MH E29.

1:23pm- camera coming from E26 and getting mandrel at E29. 

1:40pm- mandrel now at E26. Crew calling it a day due to rain. 

1:51pm- FlatCreek crew continues to grout today and currently at MH E54. 
2:36pm- MH E54 now grouted. 

2:55pm- crew is now having to go move a dozer up to the top at the quarry. No more grouting will occur today. 