Turkey Creek Ph 2 - Interceptor


Crew pumping water this morning early at MH E1. Jetter to be onsite around Noon today to clean line from E2 to E1. 
7:30am- Crew at MH E55 now to grout. 

8:35am- MH E55 now grouted. 

9:32am- MH E56 out pipe almost grouted now. 

10:57am- crew back now pumping out rest of the water in line at MH E1. 

1:45pm- jetter people have been out and looked at site and will be back out with different rig to begin jetting the line. 
We wait.

3:58pm- Mr. Rooter plumbing is now onsite to begin jetting line. 

4:33pm- crew has decided since it’s getting late to proceed on Monday with cleaning the line. Jetter emptied the 200 gallons of water it was hauling already. 