Turkey Creek Ph 2 - Interceptor
7:22am- FlatCreek crew will grout the last manhole on the project today, MH E48. Then they will be cleaning up project site.
7:45am- Ace Pipe is back onsite today starting at MH E24 heading to E26 where we left off last week.
8:26am- camera at E26. Mandrel to be pulled back to E24 now.
8:40am- camera and mandrel now at E24.
8:55am- crew now entering MH E21 to head upstream to E24.
9:30am- camera taking mandrel back downstream now towards E21 from here at E24.
9:45am- mandrel passing through E23.
9:53am- passing through E22.
9:58am- arriving at E21.
10:18am- now at MH E19 heading upstream to E21.
10:37am- now at MH E21 with camera. Mandrel to be attached and pulled back to E19.
10:46am- mandrel passing through E20.
10:52am- MH E48 now grouted. All manholes are now grouted.
10:56am- mandrel now back at E19.
11:23am- now at E16 headed to E19.
12:01pm- camera now at E19. Mandrel will be pulled back to E16.
12:06pm- mandrel passing through MH E18.
12:14pm- making drop at E17.
12:31pm- mandrel now at E16.
12:59pm- crew at E14 now headed back to E16 with camera.
1:54pm- Camera now at E16 to take mandrel back to E14.
2:08pm- mandrel passing through E15.
2:20pm- mandrel now at MH E14.
2:33pm- crew now at MH E12 going to E14.
3:05pm- camera at MH E14 pulling mandrel back now.
3:24pm- mandrel now back to E12. MH E13 was bolted down so I couldn’t get a picture of it passing through.
3:37pm- FlatCreek crew is going in MH E13 to retrieve some silt material we spotted during camera work.
3:53pm- got it dragged back from near 150’ up pipe.
4:04pm- crew mow entering MH E14. A bit of standing water I want them to look at.
Only about 3/4” for first joint or so.
Comments
Post a Comment