Turkey Creek Ph 2 - Interceptor


7:23am- Test ball is moved to MH E44 this morning. 

7:40am- MH E43 now passes vacuum test. 

7:59am- line now on test from MH E44-E43. Approximately 43 min test. 

8:41am- line from E44-E43 passes air test. 

10:00am- line now on test from MH E44-E45. Approximately 44 min test. 

10:43am- line passes air test from E44-E45. 

12:37pm- MH E44 passes vacuum teat. 

12:56pm- MH E45 passes vacuum test. 

1:27pm- line now on test from E46-E45. Approximately 65 min test. 



2:33pm- line is just barely passing. I have asked that the lines be checked for leaks due to the drop in pressure. 

Crew spraying lines with soap. 

Leaks found within last 2’ of connections and at test ball. They will bleed off pressure in test line and make repairs. 

4:44pm- crew has now fixed hoses and they are refilling the line here at MH E46-E45. I will watch it for a bit to ensure it was the testing lines and not the sewer line. 





5:27pm- test was performed for another 35+ mins or so. No movement on the gauge to speak of. Hoses were the issue. 