Turkey Creek Ph 2 - Interceptor
7:33am- crew will be testing line from E46-E47 today first thing. Test will begin shortly.

8:03am- line now on test from E46 - E47. Approximately 68 min test.
8:03am- line now on test from E46 - E47. Approximately 68 min test.
9:10am- lune passes air test from E46-E47.
9:45am- MH E46 passes vacuum test.
11:25am- crew now testing line from E48-E47. Approximately 25 min test.
12:10pm- line from E48-E47 passes air test.
12:16pm- MH E47 passes vacuum test.
1:05pm- line now on test from E48- E49. Approximately 70 min test.
2:18pm- line passes air test from E48-E49.
2:35pm- MH E48 passes vacuum test.
4:08pm- through bleeding off the air from the line test and test balls, crew is picking up on possible sewer gases. They are investigating downstream to MH E1 where the air up ball is placed to ensure it is sealed up against the pipe, thus preventing and sewer has to travel up the line.
No more testing to be done today.