Turkey Creek Ph 2 - Interceptor
7:00am-Crew figured out the issue yesterday late with the sewer gases entering the line. The ball from MH E1 was taken out and no one told the crew. It was used on another job yesterday. The crew will be reinstalling it and evacuating the line with air this morning before resuming testing.
10:14am- crew has finally got the ball installed back in E1 manhole and are currently air excavating the line.
10:50am- MH E49 passes vacuum test.
11:03am- line now on test from MH E50-E49. Approximately 68 min test.
12:10pm- line passes air test from MH E50-E49.
1:48pm- line going on test from E50-E51. Approximately 37 min test.
2:26pm- line passes air test from MH E50-E51.
3:47pm- MH E51 passes vacuum test.
4:10pm- crew will set up for a test here at MH E51 for first thing in the morning. No more testing to be done today.