Turkey Creek Ph 2 - Interceptor

Image
Ace Pipe crew to be here today to try and finish up camera and mandrel work.  7:50am- Ace Pipe has worked up the courage to cross the creek now! Headed to MH E11.  8:05am- in at E11 headed to E12 to get mandrel.  8:46am- FlatCreek crew now at MH E12 to hookup mandrel due to creek being up to high at this crossing.  9:02am- mandrel now at MH E11 from E12.  9:12am- camera will go in at E9 now and go back to E11.  10:19am- camera now at E11. Mandrel will be pulled back to E9 now.  10:51am- now going in at E7 heading back to E9 with camera.  11:17am-camera now at MH E9 from E7. Mandrel will be pulled back to E7 now.  11:32am- Mandrel now back at E7 from E9.  12:14am- camera going in at E5 headed to E7.  12:27pm- camera at E7 now. Mandrel has to be taken apart to get it into pipe for pulling back to E5.  12:58pm- Mandrel now back at E5.  1:13pm- Ace Pipe is calling it a day due to rain. 

Turkey Creek Ph 2 - Interceptor

Image
No work due to rain today. 

Turkey Creek Ph 2 - Interceptor

Image
7:22am- FlatCreek crew will grout the last manhole on the project today, MH E48. Then they will be cleaning up project site.  7:45am- Ace Pipe is back onsite today starting at MH E24 heading to E26 where we left off last week.  8:26am- camera at E26. Mandrel to be pulled back to E24 now.  8:40am- camera and mandrel now at E24.  8:55am- crew now entering MH E21 to head upstream to E24.  9:30am- camera taking mandrel back downstream now towards E21 from here at E24.  9:45am- mandrel passing through E23.  9:53am- passing through E22.  9:58am- arriving at E21.  10:18am- now at MH E19 heading upstream to E21.  10:37am- now at MH E21 with camera. Mandrel to be attached and pulled back to E19.  10:46am- mandrel passing through E20.  10:52am- MH E48 now grouted. All manholes are now grouted.  10:56am- mandrel now back at E19.  11:23am- now at E16 headed to E19.  12:01pm- camera now at E19. Mandrel will be pulled back to ...

Turkey Creek Ph 2 - Interceptor

Image
6:56am- crew at MH E1 getting pump running. Mr.Rooter plumbing to be here this morning to continue with jetting line.  7:49am- jetting is underway now.  10:19am- jetter will be getting another load of water and cleaning between E2&E3 then E2 back to E1.